Friday, August 26, 2011

Major Progress Inside and Out

They've been busy working on our house. The roof, soffit, and fascia are all in. The exterior door have also been installed. This is what it looked like this evening:




The drywall finishing/painting crew have been making really fast progress on the inside. All of the ceilings and closets have been textured with a light knockdown style. Most of the walls have been done as well in a light hand-trowled texture. It was wet when I took these pictures, so it looks dark.




Close-up of the texture (kinda looks like plaster):




The following pictures were taken a week or so ago. Joe looks like he's ready for a hoe-down in the family room: :)




We put solar tubes in the hallway, laundry room, and master bedroom closet. They will prevent having to turn the lights on in these rooms during the day. It is amazing how much light they let in. They also have an actual light built in so they can be used at night as well.


Gabi doing a little jig in her bedroom:




This is the garage...there is our front door ready to be installed...it is installed now. You can also see the attic access. There will be tons of storage in the attic above the garage.




Joe has been working on our post and pole fence. Luckily, he can use his Dad's post-hole drill which really makes things easier. Our friend Chris helped him out a lot last Sunday and they got almost 1/2 of the posts put in.


On the exterior, the trim around the windows will go in next followed by the siding. On the interior, they will start painting early next week! Then, our contractor will jump inside to install cabinets, trim, and doors. The painter will jump outside and paint the house and stain all of the trim and doors. Things are really moving!




Thanks for checking in on us! Tara

Monday, August 8, 2011

It's Coming Along...



Our new home is continuing to take shape. We are most excited that they finally closed the "skylight" and completed the truss in the front. Here is what the house looked like this evening:
Joe designed this truss and we are both really excited about how it turned out. There was a huge delay with the Douglas Fir beams that were used (but that's a long and frustrating story)...we're just glad everything is here and it's up!
The painter gave them one coat of stain before they were put up. They will be stained one more time before its done. The columns will be covered up to make them look tapered and the bases will be covered in stone. Fascia board will still be added and stained to match.

Tongue & Grove underneath to form the covered porch:

From the inside looking out:
The back of the house. The fascia board is stained the same color as the truss. The trim around the windows will be the same color as well.They've been really busy inside. The interior walls went in and then the electrical, plumbing, insulation, and ventilation rough-in work got done. They will start drywalling tomorrow!! Yay!! You can see the beams that finally arrived in this picture:Gabi & Maya in their bathtub! They love going over to the house to check things out and are pretty excited about everything!The fireplace has been framed in. We will have a wood-burning fireplace that will be surrounded by rock from the surrounding landscape from floor to ceiling. There will be built-in cabinets on both sides.We took a family outing on Sunday morning to collect rocks for the fireplace and the 4 columns in front. The girls were pretty excited about it...for awhile. I guess they don't think rock hunting is as fun as we do. ;) There are some really cool moss rocks up on the mesa. Our mason has done quite a bit of work with actual REAL rocks, so we hope it turns out nice.Here is what the truss looked like for awhile while we were waiting for the lumberyard and sawmill to get their act together (can you tell I was frustrated?? If so, it is nothing compared to how frustrated our contractor was!) :)
I guess the windows have gone in since my last post as well. They're extremely energy-efficient casement windows. These are the ones in the living room. Can you tell Joe was excited that I made him pose for a picture in front of them?


Windows & insulation in girls' bedroom. We used a combination of spray foam and fiberglass batt insulation to get a R-30 rating in the walls and a R-40 in the ceiling.

These pictures are a couple of weeks old, but you can see the interior walls. This is the living room looking towards the kitchen and guest room:
This is the kitchen looking the other way toward the living room and master/girls' bedroom and baths:The shingles and exterior finished will start going on this week as well. Thanks for checking in on us! Tara

Monday, July 18, 2011

Beams, Floors & Well

The house is coming along....we have had a few more delays due to lumber yard error and our concrete guy booked solid since he was pretty much a month behind due to the rain this Spring. Anyways, here is the what the front of our house looks like right now. The 4 posts in front of the house will be where the big truss will go. It will form a covered front porch.

The back of the house:

Here is the huge ridge beam that will be exposed in the living room/entry. The lumber yard "forgot" to order the rafters that will come off of this beam, so we have another week until those get here. In the meantime, Layne put up the I-Joists (there to hold the insulation above the area, but they will not show) and covered it as much as he could so our concrete floors could get finished:

Here is what our floors looked like before they were stained...pretty shiny due to 6 coats of sealer!
After many test samples, we decided to go with a chocolate brown color. It's a little wild for me, but Joe and Layne keep trying to reassure me that it will be fine. :) I tried to get some good pictures, because most people think we're out of our minds for putting in concrete floors (they're probably thinking it will look like a garage floor. We will grout the grooves, so it will look like large 3'x3' tiles. I've already started to look for some fun area rugs.


Finished floors in living room:

Now that the floors are done, they will lay down protective cardboard and start going crazy inside. Windows, siding, roof, interior walls, electrical, plumbing, drywall will all go in over the next couple of weeks! It seems like we've been waiting forever for the floors to get done, but now things should get moving.


They also drilled our well last week. The hit a good water source at 300 feet! Here are some pictures of the drilling rig:





I thought it was cool that the truck's front end was off the ground:


This is where the drill went into the ground:


All done:


The water line comes in next to the electrical box by the garage:



Thanks for checking in on us!!! Tara

Monday, July 4, 2011

Starting to Look Like a House!

Construction of our new house is in full swing! All of the exterior walls went up and then they got covered with plywood:

The living room windows (with transom windows above)...this area will be vaulted with exposed timbers:


The trusses went on next. I was hoping to get a picture of the crane lifting them on, but I arrived just as they finished:

They then fully enclosed the house, except for the entry/living room which will be covered with custom made trusses and rafters. The garage side:
You can kinda see the area to be timber framed below...right now it looks like a house with a huge skylight in the middle! This is the back side of the house:
Joe up in the attic area above the garage:
Maya peaking out of a window on the bedroom side:

Maya crawling on the huge ridge beams that will go in this week:


The drilling rig came last Thursday and they will start drilling the well tomorrow. We budgeted for 300 feet, so let's hope they don't have to go any deeper! :)










It's starting to become real now and we're getting even more excited. We're hoping to be in sometime in September...fingers crossed.


Tara